Resource Staffing Analysis - Hours

Additional Information

The Resource Staffing Analysis - Hours visualizer allows you to view a list of the mapped resource pool levels with the classification and net goal hours for each resource you manage. This includes resources assigned to resource pools where you are the resource pool manager or resource pool map level manager. The visualizer includes only labor for resource employees.

The visualizer displays both tentative and confirmed assignments.

For date purposes, this visualizer uses the scheduling periods from the associated Scheduling Calendar. These display as the next six scheduling periods.

Table Data

The default columns are marked with an indicator ( ). For information on how to display the optional columns, see Manage Columns.

 Column Name Description
Resource Pool Map Level

Displays the resource pool level names.

  Resource Pool Name

Displays the resource pool name.

Classification

Displays the resource class name.

Resource Displays the resource name.
Scheduling Periods

Displays the scheduling period short name and the hours in each scheduling period. The specific hours elements presented are:

  • Scheduled Hours: Displays the hours scheduled for the resource.
  • Net Goal Hours: Displays the Net Goal Hours and is calculated as: Goal Utilization Percent / 100 x Net Capacity Hours.
Total Scheduled Hours Displays the sum total of scheduled chargeable hours for the six scheduling periods displayed.