Project Scorecard (Project and Resource Management)

The Project Scorecard visualizer lists all active projects assigned to you as manager. By default the list is sorted by the Project Name. It displays Project to Date (PTD) information, which includes active projects and projects with effort, cost, or revenue activity.

For date purposes, this uses posting periods from the associated posting calendar.

When you select a project on the Project Scorecard, it populates the visualizers on the remaining areas of the system with data from the selected project.

List Data

The Project Scorecard list provides a single level of information that outlines the current status of your assigned projects. This information includes Project Name, Project Client Name, Budget Effort, Revenue, Effort, Variance, Schedule Variance Days, Unbilled Days, Receivable Days, NLM (Net Labor Multiplier), and Profit. ClosedProject Scorecard Optional Columns

Project Scorecard Optional Columns

  • All Effort
  • Currency Code
  • Effort % Complete
  • Effort Performance Index
  • Effort Remaining
  • Effort To Complete
  • Finish Date
  • Pending Effort
  • Profit %
  • Project Business Unit Code
  • Project Business Unit Name
  • Project Code
  • Project Contract Code
  • Project Contract Name
  • Project Manager Name
  • Project Market Segment Code
  • Project Market Segment Name
  • Project Service Line Code
  • Project Service Line Name
  • Project Owner Name
  • Provision
  • Resource % Complete
  • Revenue % Complete
  • Schedule Performance Index
  • Schedule Variance
  • Start Date
  • Unbilled Effort
  • Variance at Completion
  • Work Type Code
  • Work Type Name