Active Tasks Behind Schedule - Current

Additional Information

The Active Tasks Behind Schedule - Current visualizer allows you to view a list of tasks that are currently behind schedule, based on the end date and base end date. A task is considered behind schedule is based on the resources scheduled for the project. The project is selected from the Project Scorecard at the top of the tab.

By default the list is sorted by task and includes tasks where the scheduled end date is greater than the base end date. For date purposes, it uses the scheduling calendar.

Table Data

The default columns are marked with an indicator ( ). For information on how to display the optional columns, see Manage Columns.

Column Name Description
Baseline Finish Date

Displays the baseline finish date, which is the last scheduled resource completion date on the latest baseline task.

Baseline Start Date

Displays the baseline start date, which is the earliest scheduled resource date on the latest baseline task.

Days Behind

Displays the number of work days the task is behind, which is calculated as: End Date – Base End Date.

Finish Date Displays the finish date, which is the last scheduled resource completion date on the current task schedule.
Start Date

Displays the start date, which is the earliest scheduled resource date on the current task schedule.

  Task Code

Displays the task code.

  Task Hierarchy Code

Displays the task hierarchy code.

Task Name Displays the task name.