Resource Schedule - Effort

Additional Information

The Resource Schedule - Effort visualizer allows you to view a summary of resource effort value whose assigned resource pools you manage, either through the resource pool manager or map level manager designation.

The data in this visualizer is derived from resource scheduling and is restricted to labor or employee resources. The visualizer displays tentative and confirmed assignments.

For date purposes, this visualizer uses the scheduling periods from the associated Scheduling Calendar. The twelve scheduling periods display as the current scheduling period and eleven scheduling periods in the future.

Chart Data

All data in this chart is derived from resource scheduling and calendar information.

Area Description
Effort The left-side of the chart, or the y-axis, displays effort values.
Time

The area below the chart, or the x-axis, is divided into twelve scheduling periods. The scheduling periods are based on the selected Scheduling Calendar for the project.

Chart

The chart includes the following information.

  • Scheduling Period: Displays the Scheduling Period short name.
  • Tentative: Displays assignments that have been assigned but not yet accepted as a stacked column.
  • Confirmed: Displays assignments that have been assigned and accepted as a stacked column.