Project Status Summary

The Project Status Summary visualizer allows you to view a snap shot list of all To Date (TD) information as of the current date.

For date purposes, this visualizer uses the posting period from the associated Posting Calendar.

Table Data

All data in this table is derived from organization and project information.

  Area Description
Budget Effort Displays the budget effort.
Effort To Complete Displays the effort to complete.
  Office Displays the office name.
  Organization Code

Displays the project organization code.

  Organization Company Code

Displays the project organization company code.

  Organization Company Name

Displays the project organization company name.

Organization Map Level 4 - 6 Name

Displays the organization map level name.

Organization Name

Displays the organization name.

  Project Code

Displays the project code.

Project Finish Date Displays the project end date.
Project Manager Name Displays the project manager name.

Project Name

Displays the project name.

Project Start Date Displays the project start date.
Region Displays the region name.
Revenue % Complete

Displays the revenue percent complete which is calculated as Revenue / Budget x 100.

Schedule % Complete

Displays the schedule percent complete which is calculated as TD Effort / (TD Effort + Effort To Complete) x 100.

Scheduled Effort Displays the total scheduled effort.
TD Effort

Displays the cumulative to date effort.

TD Revenue

Displays the cumulative to date revenue.

  TD Provision Displays the revenue provision for the project.
Variance At Completion

Displays the variance at completion which is calculated as: Effort Budget - (TD Effort + Effort to Complete).