12 Week Staffing Outlook - Hours
The 12 Week Staffing Outlook - Hours visualizer allows you to view a summary of employees assigned to your resource pool and/or resource pool map profile. The visualizer displays both tentative and confirmed assignments.
The timeframe includes only labor transactions for employees.
For date purposes, this visualizer uses the scheduling dates from the associated Scheduling Calendar. The twelve weeks display as the current week and eleven weeks in the future.
Chart Data
All data in this chart is derived from resource scheduling and calendar information.
| Area | Description |
|---|---|
| Hours | The left-side of the chart, or the y-axis, displays scheduled hours. |
| Time |
The area below the chart, or the x-axis, is divided into scheduling dates. The scheduling dates are based on the selected Scheduling Calendar for the project. |
| Chart |
The chart includes the following information. Capacity is a line that displays above the stacked columns of confirmed and tentative hours:
|